Location: Selby Street, Jolimont, Western Australia
Client: PS Structures
Architect: dwp | Suters
Value: $620K
DENMAC Deliverables:
  • Facade Cladding ($400K)
  • Architectural Metalwork and Glass package – balustrades, handrails and security bollards ($220K)
Status: Completed December 2014
  • Architectural External Cladding
  • Architectural Glass
  • Architectural Metalwork
  • Commercial Metalwork
  • Facades
  • Modular Facade Construction

The construction phase of the project was a twelve-week lead time due to the custom colour material selected by the architect. Staggered panel alignment and angles were a challenge during the installation phase of the project, but handled with ease by DENMAC’s install team due to calibre of the design work produced by our in-house Design team.

Security bollards and carpark bollards, court side balustrade and handrails, and more than twenty feature sunshades were all installed by DENMAC. The sunshades required attention to detail due to each of them having a unique shape or the mosaic of colours that the Alucobond panelling had to achieve.